Importing Goods into Australia: Customs, Duties, GST and Biosecurity / Building Industry Licensing by State: Who Needs What / Hiring in Healthcare: How Clinics Recruit Doctors and Nurses / Warehouse Rents by City: Industrial Property Benchmarks / 3PL Warehousing Costs per Pallet and When to Outsource / Payment Claims and Adjudication: A Step by Step Guide / Commercial Leases for Small Business: Rent Reviews, Outgoings and Make Good / Selling a Business Premises: Freehold vs Leasehold / Hotel Bathroom Amenities: Refill Dispensers vs Minis, Costs and Waste Rules / Combining Work Trips with Volunteering Days / Duty of Care for Staff Travelling Overseas / Psychosocial Hazards: Employer Obligations by State / Importing Goods into Australia: Customs, Duties, GST and Biosecurity / Building Industry Licensing by State: Who Needs What / Hiring in Healthcare: How Clinics Recruit Doctors and Nurses / Warehouse Rents by City: Industrial Property Benchmarks / 3PL Warehousing Costs per Pallet and When to Outsource / Payment Claims and Adjudication: A Step by Step Guide / Commercial Leases for Small Business: Rent Reviews, Outgoings and Make Good / Selling a Business Premises: Freehold vs Leasehold / Hotel Bathroom Amenities: Refill Dispensers vs Minis, Costs and Waste Rules / Combining Work Trips with Volunteering Days / Duty of Care for Staff Travelling Overseas / Psychosocial Hazards: Employer Obligations by State /
WX

SYDNEY 22° / MELBOURNE 16° / BRISBANE 27° / PERTH 30° / ADELAIDE 24° / HOBART 12° / CANBERRA 14° / DARWIN 33°

Home/Policy & Regulation/Guide
Policy & Regulation14 NOV 2026 / 9 MIN / Updated 18 NOV 2026

Payment Claims and Adjudication: A Step by Step Guide

How a security of payment claim moves from invoice to adjudicator's decision, with the NSW deadlines in order and how Queensland, Victoria and WA differ.

By VLD Business Desk, Construction and trade writer

Two construction workers in hard hats at an outdoor site with a wheelbarrow
Two construction workers in hard hats at an outdoor site with a wheelbarrow · Photo: Mikael Blomkvist / Pexels

The brief

  1. 01In NSW and Victoria a payment schedule is due within 10 business days of a payment claim, or sooner if the contract says so; Queensland and WA allow 15.
  2. 02A respondent who misses the payment schedule deadline becomes liable for the full claimed amount in every one of those four states.
  3. 03In NSW a claimant has 10 business days after receiving a short payment schedule to lodge an adjudication application.
  4. 04NSW adjudicators must decide within 10 business days of accepting the application unless the parties agree to more time.
  5. 05Reasons left out of the payment schedule cannot be raised for the first time at adjudication in NSW, Queensland, Victoria or WA.

Fifteen business days is the longest a head contractor in NSW can be made to wait for a progress payment, and the payment claim adjudication process exists to enforce that. Every Australian state has a security of payment law built on the same idea: pay now, argue later. If you send a valid payment claim and the other side does not answer properly in time, you can take the dispute to an independent adjudicator and get a binding decision within weeks rather than years.

How security of payment works in plain terms

Security of payment laws give anyone who carries out construction work or supplies related goods and services under a contract a statutory right to progress payments. The NSW law is the Building and Construction Industry Security of Payment Act 1999, administered by Building Commission NSW.

The system runs on four documents: the payment claim, the payment schedule, the adjudication application and the adjudication response. Each has a hard deadline counted in business days, and a missed deadline usually decides the outcome. Courts have repeatedly treated the time limits as strict.

You'll need:

  • A written or oral construction contract and your claim records (progress photos, delivery dockets, variation instructions)
  • The correct service address for the other party, as set out in the contract
  • A calendar that counts business days and excludes 27 to 31 December in NSW
  • Time: about 4 to 8 weeks from claim to decision if it goes to adjudication
  • Skill level: manageable for a simple claim, but advice is wise above about $50,000 or on any disputed variation
Hand holding a company invoice on a clipboard with a pen
Hand holding a company invoice on a clipboard with a pen · Photo: Kindel Media / Pexels

Before you start: check the Act applies

The NSW Act covers most construction contracts carried out in NSW, including subcontracts, supply of materials and professional services such as design. It does not cover claims against a resident owner under a residential building contract for work on their own home, and some contracts where payment is not referable to the value of work.

Check your contract for its payment terms. In NSW, any clause allowing more than 15 business days for a head contractor or 20 business days for a subcontractor after the claim is served is void to the extent of the excess, under section 11. Contracts can set shorter times, and those shorter times apply.

Step 1: Serve a valid payment claim

From October 2019, NSW contracts give an entitlement to claim on the last day of each named month, and also after termination. A payment claim must identify the construction work or related goods and services, state the claimed amount, and state that it is made under the Act.

Tip and common mistake

Tip: attach a schedule that lists each item, its contract value, the percentage complete and the amount claimed, because the adjudicator can only award what the claim supports. A frequent mistake is leaving out the "made under the Act" statement, which is still required in NSW, Victoria and WA but not in Queensland.

Head contractors serving a claim on a principal must also attach a supporting statement declaring that all subcontractors have been paid. Serving a claim without one, or with a false one, is an offence.

Step 2: The respondent replies with a payment schedule

The respondent has the earlier of the contract period or 10 business days to provide a payment schedule. It must identify the claim, state the amount it proposes to pay, and give every reason for paying less than the claimed amount.

This is the document that sets the battle lines. Under section 20(2B), the respondent cannot raise new reasons in its adjudication response that were not in the payment schedule. A vague schedule that says "work defective, refer to site records" invites a determination in the claimant's favour.

What happens if no schedule arrives

A respondent who misses the deadline becomes liable for the full claimed amount. The claimant can then choose between two paths: recover the debt in court, where the respondent cannot bring a cross claim or raise defences about the work, or go to adjudication after giving notice.

Two professionals in hard hats reviewing construction plans on a laptop
Two professionals in hard hats reviewing construction plans on a laptop · Photo: Thirdman / Pexels

Step 3: Decide whether to apply for adjudication

You can apply for adjudication in three situations, each with its own clock under section 17 of the NSW Act.

SituationWhat the claimant must doNSW deadline
Payment schedule is less than the claimLodge the adjudication applicationWithin 10 business days after receiving the schedule
Schedule was given but the scheduled amount is unpaidLodge the adjudication applicationWithin 20 business days after the due date for payment
No payment schedule and the claim is unpaidGive notice of intention, wait 5 business days for a late schedule, then lodgeNotice within 20 business days after the due date, then apply within 10 business days after the 5 day window ends
Source: Building and Construction Industry Security of Payment Act 1999 (NSW) s 17, via AustLII and Building Commission NSW (checked November 2026).

Applications go to an authorised nominating authority (ANA), a private body authorised by Building Commission NSW, which refers it to an adjudicator. The application must be in writing, identify the claim and schedule, and include the submissions and documents you rely on. A copy must be served on the respondent.

Step 4: The respondent lodges its adjudication response

Under section 20, the respondent can lodge an adjudication response within 5 business days after receiving a copy of the application, or 2 business days after receiving notice of the adjudicator's acceptance, whichever is later. If no payment schedule was provided at all, there is generally no right to lodge a response.

The response may only include reasons already set out in the payment schedule. Its job is to support those reasons with evidence, such as a quantity surveyor's report, defect photos or correspondence.

Tip and common mistake

Tip: claimants should read the response the day it arrives and check it against the schedule. If it raises a new reason, say so in writing to the adjudicator. A common error by respondents is relying on a contractual set off that was never mentioned in the schedule.

Step 5: The adjudicator decides

The adjudicator must decide within 10 business days after notifying the parties of acceptance, or a longer time if the claimant agrees, according to section 21. The decision covers the amount payable, the date it is due, the interest rate, and how the adjudicator's fees are split between the parties.

An adjudicator can only consider the Act, the contract, the payment claim and schedule, the submissions properly made, and the results of any inspection. They cannot take into account material lodged out of time.

In practice, adjudicators value each disputed item on the evidence in front of them. A claim that pairs each line with a dated photo, a delivery docket or a signed variation tends to fare far better than a lump sum backed by a covering letter, and a respondent's reason backed by an independent quantity surveyor's valuation carries more weight than a site manager's email.

Step 6: Payment or enforcement

The respondent must pay the adjudicated amount within 5 business days after the determination is served, or on the date set by the adjudicator, whichever is later. If it does not pay, the claimant can request an adjudication certificate from the ANA and file it in court as a judgment debt.

Claimants also have pressure tools. A claimant who is not paid can suspend work after giving 2 business days' notice, and a subcontractor can ask the principal to pay money owed to the head contractor directly to them through a payment withholding request.

Two workers on scaffolding laying a brick wall under a cloudy sky
Two workers on scaffolding laying a brick wall under a cloudy sky · Photo: 女子 正真 / Pexels

How do the other states compare?

The four big state regimes share the pay now, argue later design but differ on almost every deadline. A team running a single 15 day cycle across states will be late in NSW and Victoria.

FeatureNSWQLDVICWA
Payment schedule due10 business days15 business days10 business days15 business days
"Made under the Act" wordingRequiredNot requiredRequiredRequired
Adjudication application window10 to 20 business days20 to 30 business days5 to 10 business days20 business days
Payment terms cap15 head / 20 sub15 head / 25 sub20 business days20 head / 25 sub
Review of a determinationCourts onlyCourts onlyCourts onlyReview adjudication over $200,000 gap
December pause27 to 31 Dec22 Dec to 10 Jan22 Dec to 10 Jan22 Dec to 10 Jan
Source: SUMIT, "Security of payment compared: NSW, Queensland, Victoria and WA", citing each state's Act as at 14 October 2026.

Victoria's Act changed materially on 15 April 2026, abolishing reference dates and the old excluded amounts review, so older Victorian guides are unreliable. In Queensland, missing the schedule deadline is also an offence under the BIF Act, and the respondent loses its right to an adjudication response. WA's amendment bill passed its third reading in the Legislative Council on 13 October 2026, so check the WA Parliament site for commencement.

Worked example: a Sydney plasterer's claim

Here is an example. A plastering subcontractor on a Parramatta apartment job serves a payment claim for $84,000 on 30 June. The head contractor's schedule arrives on 10 July proposing $41,000, citing "incomplete set out on level 4" and nothing else.

  1. The plasterer has 10 business days from 10 July to lodge an adjudication application with an ANA.
  2. The head contractor's response can only argue the level 4 set out point. Its later concern about ceiling defects on level 2 cannot be raised, because it was not in the schedule.
  3. The adjudicator decides within 10 business days of accepting. If $70,000 is awarded, the head contractor must pay within 5 business days of being served.

The head contractor can still sue later over the level 2 defects, but it must pay first.

Common mistakes on both sides

Claimants

  • Serving on the wrong address or by a method the contract does not allow
  • Claiming for work outside the contract without variation evidence
  • Counting calendar days instead of business days, or forgetting the December pause
  • Lodging the application one day late, which usually ends the claim

Respondents

  • Sending a schedule that gives a number but no reasons
  • Assuming the contract's 30 day response period applies, when the Act caps it at 10 business days in NSW
  • Treating a claim emailed to a project manager as informal when it is valid under the contract

When to get professional help

A small, clean claim can be run by a contractor with good records. Get advice if the claim is over about $50,000, involves disputed variations or delay costs, follows a termination, or crosses state lines. Respondents should get advice the day a claim arrives, since the 10 day schedule window leaves little time to gather evidence.

Construction law firms handle these disputes daily and can often prepare an adjudication application or response within the tight timeframes. Specialist security of payment lawyers such as CCS Legal act for contractors, subcontractors and principals, and a short review of your payment claim before it is served can avoid the technical errors that sink otherwise strong claims.

What to do next

Treat every payment claim as the start of a legal process with fixed deadlines. Claimants should use the correct wording, serve it properly and diarise every business day deadline. Respondents should answer within 10 business days in NSW with every reason they will ever rely on. Whichever side you are on, put the deadlines in the calendar before you do anything else.

Sources

  1. NSW Government, "About Security of Payment for construction contractors", accessed 18 November 2026, https://www.nsw.gov.au/housing-and-construction/compliance-and-regulation/security-of-payment/about
  2. NSW Government, "Responding to an adjudication application", accessed 18 November 2026, https://www.nsw.gov.au/housing-and-construction/compliance-and-regulation/security-of-payment/responding-to-an-adjudication-application
  3. AustLII, Building and Construction Industry Security of Payment Act 1999 (NSW) s 17, accessed 18 November 2026, https://www.austlii.edu.au/au/legis/nsw/consol_act/bacisopa1999606/s17.html
  4. AustLII, Building and Construction Industry Security of Payment Act 1999 (NSW) s 21, accessed 18 November 2026, https://www.austlii.edu.au/au/legis/nsw/consol_act/bacisopa1999606/s21.html
  5. AustLII, Building Industry Fairness (Security of Payment) Act 2017 (Qld) s 79, accessed 18 November 2026, https://www.austlii.edu.au/cgi-bin/viewdoc/au/legis/qld/consol_act/bifopa2017514/s79.html
  6. SUMIT, "Security of payment compared: NSW, Queensland, Victoria and WA", 12 August 2026, accessed 18 November 2026, https://www.sumitconsulting.com.au/news-insights/sopa-comparison-nsw-qld-vic-wa
  7. NSW Government, "Payment claim and adjudication flow chart", accessed 18 November 2026, https://www.nsw.gov.au/housing-and-construction/compliance-and-regulation/security-of-payment/about/claim-flow-chart
  8. Adjudicate Today, "NSW adjudicator's time for determination", accessed 18 November 2026, https://www.adjudicate.com.au/nsw/adjudication/adjudicators-time-for-determination

FAQ

What makes a valid payment claim in NSW?

It must identify the work or goods, state the amount claimed, and state that it is made under the Building and Construction Industry Security of Payment Act 1999. Head contractors also need a supporting statement declaring that subcontractors have been paid.

What happens if I do not send a payment schedule?

You become liable for the full amount claimed. In NSW the claimant can recover it as a debt in court, where you cannot raise defences about the work, or go to adjudication after giving you a notice and a final 5 business days to respond.

How much does adjudication cost?

Adjudicators charge fees set by each authorised nominating authority, usually by the hour, and the parties normally share them equally unless the adjudicator orders otherwise. Legal costs are generally borne by each party.

Is an adjudication decision final?

No. It is an interim decision that must be paid, but either party can still pursue its full contractual rights in court or arbitration later. Courts will only set a determination aside for jurisdictional error or a denial of natural justice.

Does security of payment apply to home renovations?

In NSW, claims against a resident owner under a residential building contract are excluded, so it mainly protects contractors and subcontractors in the commercial chain and those working for developers.

About VLD Business Desk

Business and small business writers

VLD Business Desk is the VLD editorial byline for business and small business writers. Articles are researched from official and primary sources, which are listed at the end of each piece.

WX

Capital cities

  • SYD24° / 16°
  • MEL18° / 12°
  • BNE29° / 20°
  • PER32° / 21°
  • ADL26° / 17°
  • HBA14° / 8°
  • CBR17° / 6°
  • DRW34° / 25°

INDICATIVE

Markets & trade data

  • ASX 2008,142.30▲+0.74%
  • AUD/USD0.6642▼−0.21%
  • AUD/EUR0.6094▲+0.05%
  • Iron Ore$104.20▲+1.12%
  • Brent Crude$82.15▼−0.48%
  • Gold$2,431▲+0.36%
  • BHP$44.28▲+0.82%
  • CBA$118.40▼−0.14%

ASX, NYSE, indicative

VLD Daily, before the bell.

Subscribe

More from the Policy & Regulation desk

Work with VLD

News tips

Seen something in your industry we should know about? Tell the desk.

Send a tip

Advertising

Reach owners, operators and decision makers across Australia.

Advertise with VLD

Partnerships

Events, research and content partnerships with VLD.

Talk to the desk